Roofing Projects in Akron, OH

Take a look at some of our best projects below

Ironrock - Building #1 - Canton, Ohio

  • Spray foam roofing over existing TPO
  • 31,200 square feet
  • 15-year, renewable, NDL, NPR warranty granted
  • Average 1.5" thickness of 3lb. spray foam
  • Basecoat of 15 mil thickness of high-solids silicone coating
  • Topcoat of 10 mil thickness of high-solids silicone coating
  • Granules embedded into topcoat
  • New custom-fabricated (in-house) metal perimeter detail around edges
  • All perimeter metal walls prepped and coated with HS silicone
  • Completed July 2025

Coventry Schools - Modular Classroom Unit - Akron, OH

  • Spray foam roofing over existing EPDM
  • 10,946 square feet
  • 20-year, renewable, NDL, NPR warranty granted
  • 1/2" high-density coverboard installed over EPDM
  • All 22 existing drains removed. Replaced with new gutter system, improving drainage
  • New 24-guage, Kynar finished, custom-fabricated foam stop installed along perimeter edge
  • Average 1.5" thickness of 3lb. spray foam
  • Basecoat of 20 mil thickness of high-solids silicone coating
  • Topcoat of 10 mil thickness of high-solids silicone coating
  • Granules embedded into topcoat
  • Completed August 2025

Peoples Services - Marvo - Bldg 8 Northern Lower Area - Akron, OH

  • Spray foam roofing over existing Metal
  • 123,000 square feet
  • Flush panel and skylights covered with OSB
  • 25-year, renewable, NDL, NPR warranty granted
  • Average 2" thickness of 3lb. spray foam
  • Basecoat of 15 mil thickness of high-solids silicone coating
  • Topcoat of 15 mil thickness of high-solids silicone coating
  • Granules embedded into topcoat
  • New custom-fabricated (in-house) metal perimeter detail around edges
  • Completed May 2025

GAR Foundation - Akron, Ohio

  • Silicone roof coating system over existing EPDM
  • 2,748 square feet
  • 20-year, renewable, NDL, NPR warranty granted
  • Install single-ply primer
  • Install acrylic bleed blocker
  • Raised NE section of roof to receive new 24-gauge, Kynar finished counterflashing
  • Basecoat of 15 mil thickness of high-solids silicone coating
  • Topcoat of 15 mil thickness of high-solids silicone coating
  • Project completed May 2024

Coventry Local Schools-Elem & Middle School - Akron, OH

  • Spray foam roofing over existing EPDM
  • 61,187 square feet
  • 20-year, renewable, NDL, NPR warranty granted
  • 1/2" high-density coverboard installed
  • Average 1.5" thickness of 3lb. spray foam
  • Basecoat of 20 mil thickness of high-solids silicone coating
  • Topcoat of 10 mil thickness of high-solids silicone coating
  • Granules embedded into topcoat
  • New custom-fabricated (in-house) metal perimeter detail around edges
  • Project completed July 2023

People's Services - Marvo - Building 8 - Northern Low Area

  • Project Type: Spray foam roofing installed over an existing metal roof
  • Building Type: Distribution Center
  • City: Akron, Ohio
  • Size: 123,000 square feet
  • Time to Complete: 37 days
  • Year Completed: 2024

Bernard Mechanical-Section 1-6

  • Project Type: Spray foam roofing installed over an existing EPDM roof
  • Building Type: Heating and Cooling Contractor
  • City: Akron, Ohio
  • Size: 10,850 square feet
  • Time to Complete: 3 days
  • Year Completed: 2023